^I seem to recall that when the first iOn vehicle was delivered, it was a couple of months before it was seen outside or made test runs. That initial period was spent doing static tests, checking clearances in the maintenance building, setting up maintenance equipment, doing staff familiarization, etc etc.
There is a lot of new maintenance equipment that is also nice and shiny, and needs to be fitted out. For instance, I’m sure there is a hoist or jacking station. Suppose you eagerly start running the car, and find something is amiss, and needs checking out.....but you’ve never used the hoist before. Smart operators do some practice hoisting before the car starts its tests.
In other words, all is well so far.
- Paul