I sure hope it won't be like Waterloo:
BBD: "Hey we've got some of your trains ready."
Region: "We don't want them until we've got our FIE figured out "
BBD: "How about now? We've built a bunch more, they're really shiny."
Region: "Nah, we're good."
BBD: "Look, these things are starting to pile up, and you really should have your FIE sorted out by now."
Region: "Okay, we'll take like, half."
BBD: "Alright. Say, how's that FIE coming along anyway?"
Region: "We've picked it out, will you install it for us?"
BBD: "Sure, have your lawyers call our lawyers to work out a contract."
- time passes -
Region: "The first bits of FIE will be there in July."
BBD: "Seriously, July? We had the first production train ready like a year ago."
Region: "Yeah, we know. Oh, can you get it all installed and commissioned by September? We've got a deadline to meet."
BBD: "We'll do our best."
- September deadline passes -
Region, to press: "It's all Bombardier's fault!"
(Note: I'm pretty sure that a lot of the region's FIE delays fell at the feet of Metrolinx, as I have a vague recollection that they were going to spec it, but still...)