Six Point Interchange is about to get very busy even more. See below...
Notice to Property Owners & Residents PHASE 1A Re: St Albans Sanitary Sewer Replacement July 9, 2019 Dear Neighbour, You are receiving this notice because you are situated near or adjacent to the proposed sanitary sewer replacements on St Albans Road, where construction activities will commence shortly.
The 6 to 7 week duration of this project is expected to take place from July 15 th – August 31 st, 2019. Initial activities will begin on the east side of St Albans Road and work its way west towards Auckland Road. The construction will consist of an open-cut excavation to upgrade the existing sanitary sewer infrastructure. The work will be undertaken by Concert Properties, the developer of the KIP 2 located at 5365 Dundas St. W., on behalf of the City of Toronto. R.V. Anderson Associates Limited was retained by Concert Properties Ltd. to design the modifications to municipal infrastructure, and to oversee the construction to assure that the work is completed in accordance with the City and Provincial rules and regulations. In order to minimize the disruption caused by this construction, work will take place in multiple phases.
Public Information notifications will be provided for each of the construction phases. This notice is for phase 1A for which the construction schedule is provided below. The figure of the traffic management measures for this phase is provided on the reverse side of this notice. Access to all buildings and services (i.e. garbage collection, emergency vehicles, entrances and exits to parking garages, or any other usual services) will be maintained. Every effort has been made, with City staff support, to complete all works with minimal disruption to the public, businesses and residents alike. We apologize for any inconvenience this may cause and appreciate your cooperation understanding.
Construction Schedule: PHASE 1A - July 15 th, 2019 to July 17 th, 2019 Work Hours: 7:00 a.m. to 7:00 p.m., Monday through Friday 9:00 a.m. to 6:00 p.m., Saturday For enquiries or concerns, kindly contact 311 or for site specific information contact the following persons: Consultant: Contractor: R.V. Anderson Associates Limited GFL Environment Adrian Ranganathan (Primary) Tony Tassone Site Representative Site Supervisor
aranganathan@rvanderson.com ttassone@gflenv.com Cell: (647) 710-6360 Office Tel.: (905) 760-9799 Please turn over Notice to Property Owners & Residents PHASE 1A If you have any questions or require further information, please contact us at the phone numbers provided. c: City of Toronto Concert GFL Phase 1A Closed Road