They're not repaving, they're paving for the first time. I guess the staging of the project is such that they want to reroute the lanes to one side of the structure in an initial stage, or maybe rebuild the walls to start with. Either of those options would require the lanes to be moved into or across the area formerly occupied by the median - thus the paving through there.I'm surprised they are repaving before the girders below have been replaced for that section. I just assumed they could only be replaced when nothing is on top but I guess that is not the case.