drum118
Superstar
Oct 28
The 2nd eastbound lane should be pour this week as it is form for it west of Carlaw for one block. Curb been place for the 2nd block as well some form for the curb lane.
Nothing else up to the new bridge with hydro ducting being installed where the light post are to go.
There are places where they could form and pour the 3rd lane, but expect it will be done after the eastbound traffic is shifted to the new lanes.
Traffic cannot use the new eastbound lane bridge until the intersection for Don Roadway is build as well the ability to shift traffic back to the current road configuration since the new eastbound lanes will not be ready until Q2 2024.
Once the traffic is shifted to the new bridge, the westbound can be remove to allow the building of the new one.
Both the current eastbound lanes west of the new bridge as well the bridge is ready for paving.
More up on my site
The 2nd eastbound lane should be pour this week as it is form for it west of Carlaw for one block. Curb been place for the 2nd block as well some form for the curb lane.
Nothing else up to the new bridge with hydro ducting being installed where the light post are to go.
There are places where they could form and pour the 3rd lane, but expect it will be done after the eastbound traffic is shifted to the new lanes.
Traffic cannot use the new eastbound lane bridge until the intersection for Don Roadway is build as well the ability to shift traffic back to the current road configuration since the new eastbound lanes will not be ready until Q2 2024.
Once the traffic is shifted to the new bridge, the westbound can be remove to allow the building of the new one.
Both the current eastbound lanes west of the new bridge as well the bridge is ready for paving.