Torbram Rd is now 100% grade separated, but not finished.
Surprised Halton Sub separation is still not finish. The handrail for the east sidewalk is missing as well some grading. Looks like still some roadwork for the northbound lanes still to be done.
The Weston Sub northbound lanes are open, but still back filling to be done on the east side, as well the top of the retaining wall. Was able to walk along the east sidewalk. A good chunk of the west retaining wall on the north side in place and could be all in place by year end. The south side is having the base of the retaining wall pour by year end and fully done by spring. By the summer, the whole thing should be finish.
Everyone is now happy as there is no more traffic disruption by trains and the trains don't have to slow down as much before for the construction as well traffic.