When I said "The ROW on St Calir cost less around 170 million" what I meant to say was it cost less than 170 million. And the reason I used 170 million was because i knew it was over 100 million but could not remember for sure how much. And it did not cost 60-65 million as you say. It was originally projected at 48 million, then revised to 65 million and then estimated at 106 million. I am not even sure if that the final figure because that was before the last 300 metres were built and who knows if that part went over
The total cost of the project was
$106 million according to TTC's post-mortem - most of the work was completed at that time, and I didn't see any additional funding requests beyond that. The TTC budget was $65 million in 2005 with 2 years of construction being completed in 2006. $30 million of the additional cost this was for the project the added on late to put Hydro Underground. There were also costs related to enhanced street lighting, relocation of hydrants, and sidewalk and roadway enhancements.
Even if you only assume the only out-of-budget item was the $30 million for Hydro, then at worst it increased 17% from $65 million to $76 million. Which isn't bad given there's a few years of inflation in there, with some of those years seeing the inflation rate for construction at over 5% a year.
The two main reason that the cost went up, was the huge increase in scope, and the delays in the project - from the scope changes and the judicial review (remember that the judge in charge of the judicial review,
Ted Matlow, was was found guilty of misconduct relating to his bias against the city).
So with a 6.8 km length, the cost was either $9.6 million/km or $11.2 million/km, depending on whenever you consider the extra $11 million was non-TTC scope, or just overspending.
Either way, it's not the disaster that some pretend.
But who is to say the same thing or some of it won't happen again for the other LRT lines causing them to go overbudget
Isn't that the whole point of the post-mortem? To learn from the mistakes, and not repeat them? To consult with the community early, rather than late - haven't they been doing this on the Transit City lines? To define the scope initially, rather than late - which they had also been doing - though Rob Ford seems to be hell bent to change the scope half-way through ... fortunately council has set that straight. To avoid all the small contracts, and do general contracting - haven't they been doing this?
TTC hasn't had a problem doing the big projects on-time, on-budget. The Sheppard line came in on budget. The Downsview station was on budget as far as I recall. All reports are that the Spadina extension is on budget.