AHK
Senior Member
Doesn't look like much progress at all with this site.
This is one of the more interesting sites with respect to the shoring and excavation process - two different elevations (track level, top of the berm, and street level on the Esplanade frontage) combined with a relatively narrow site. The shoring on top of the berm was done first, and then excavation of the berm was done to bring the south part of the site down to ground level, so shoring could be done along Esplanade and beside the Green P parking garage entrance.
I guess if you just look at the flat piece of ground with the shoring along Esplanade underway, it may look like not much has happened - but the site sure did not start out that way.