Had to drop off a lens for repairs and this allow me to have a look at Milliken and Agincourt station. As of this visit, both stations are now cross off my shooting list.
Until track 1/2 is in place, the stations are basely done with minor work still staking place,
Milliken
No screens on platform 2 and the ones that are working on platform 1 have no schedule time for trains. A number of screens not working.
Track 2 needs the rails splice in the station area as well ballast and level that can happen until the tracks are install at either end when every that will be.
Crews working on electrical and mechanical items on the northside of Steeles.
Took a walk across the bridges and a nice view
Agincourt
Until track 1 is built at either end of the station, can't use that platform.
Only one screen working showing only northbound trains starting at 1529 for 5 trains only.
Small minor things still been worked on out of sight that it is basely done.