Stouffville Corridor Part I Newsletter
Thank you for signing up for Metrolinx's Scarborough-Markham e-newsletter for Part I (Sheppard to Steeles). Community engagement is important to us. Our goal is to keep you informed about our railway expansion program and its benefits and impacts to your community. We encourage you to share this information with your neighbours. Please forward us any questions you have about the work in your neighbourhood. Please forward us any questions you have about the work in your neighbourhood.
In this edition, our update includes:
- Road closures this weekend at Huntingwood and Havendale
- Agincourt and Milliken GO Station Update
- Construction Update
- Community Office Hours
Road closures this weekend and next at Huntingwood and Havendale
As part of the our improvement to railway crossings, Metrolinx is undertaking Mainline Track Rehabilitation at the railway corridor at Havendale Road and Huntingwood Drive.
In order to safely complete this work, Metrolinx has coordinated with the City of Toronto to close Huntingwood Drive between Belgreen Avenue and Kittery Blvd, from Friday November 9th at 9:00pm, through to Monday November 12th, re-opening at 5:00am. This intersection will also be closed the following weekend at the same times, from Friday November 16th to Monday November 19th.
In addition, Havendale Road will be closed for one weekend, between Stainforth Drive and Belgreen Avenue from Friday November 16th, starting at 9:00pm, through to Monday November 19th, re-opening at 5:00am.
Stations Work Update
Construction at Agincourt, Milliken, and Unionville GO Station's began on October 1, along with work on the Steeles Avenue Grade Separation.
This project is expected to last approximately two years in total, to the end of 2020 (early 2021 for Steeles Avenue Grade Separation).
At Agincourt, as of October 22, EllisDon began work in the former motel plot of land. This work is to prepare the location for temporary parking that will be used while EllisDon completes removals for the south portion of the platform that began on October 29. Construction crews will be isolated to this portion of land (former motel area) and will not be occupying the existing station footprint. EllisDon has indicated that a mini excavator and bobcat skid steer will be the equipment being used.
Construction Update (Non-station work)
Work Performed/Construction activities:
- Removed soft soil from the subgrade area (portion right below surface) as well as sub-excavated soft soil below subgrade
- The sub-excavated area is being backfilled with sub-ballast material
- Installing pandrol clips (used to fasten rail tracks ad secure them) with ties and rails of south track from Huntingwood to Finch Avenue crossing
- Installing Bell 360 ducts in the trench along the west property line in between Huntingwood and Finch Avenue crossings
- Installing fast fences along the west property line in between McNicoll spur to Passmore Avenue crossing
- Approving competent subgrade
Work scheduled for weekdays work:
- Dewatering (When required)
- Grading subgrade for south track from Cascade spur to Finch Avenue crossing (progressing)
- Extra removal of poor subgrade (when required)
- Concrete ties and rail distribution from Marilyn Finch Avenue crossing (complete)
- Huntingwood Avenue north track (weekend work)
- Installing Bell 360 duct in between Finch and Huntingwood crossing