The suggestion of progress is just an illusion. Note the red flags on Track 1 (the new track is Track 0). Both tracks are missing north of the underpass, up to about Rogers Road. Supposedly to enable preliminary works for the St Clair Smarttrack station. The Kitchener line is down to two tracks at the moment.
My conspiracy theory is that there is some other item that is critical path and not immediately doable (my double conspiracy theory is that it is tied to the Crossways-TTC connection, which is progressing but has lots of work left to do), so the project has deferred all other parts as it's not the last minute yet. Or perhaps as suggested, funding has been yanked to cover some other overspend.
In any event, there is a basket of work that has to be completed before that new track has any real purpose
- Finish preliminary grading and lay trackage from Strachan up to Bloor
- Relocate a signals bungalow at Parkdale and/or grade and lay a new Barrie line track Strachan to Parkdale
- Complete the Randolph entrance to allow pedestrian access under the new track
- Add a turnout and control point at Black Creek to tie in the freight interchange to CPKC to the new track
- Restore the segment between St Clair and Rogers Road for Tracks 0 and 1
This whole project seems like a hobby farm that ML pokes at once in a while when spare change is available.
- Paul