TerryJohnson
New Member
With income for the proponent dependent on operating revenue, not having the proponent operate misaligns incentives needed to ensure success.
With O in there with revenue risk exposure, we have the opportunity for the proponent to invest in additional frequencies, additional classes, potentially even shorter travel time.
What would the optimal implementation model be in your mind?
Transport Action's position, based on member and supporter polling, is that DBFM infrastructure is reasonable but that passenger rail operations belong in the public sector. There's slightly less aversion to private sector operation of a completely new Calgary-Edmonton project than to outsourcing VIA's existing corridor. The level of concern around the future of VIA Rail and services outside the corridor if corridor operations are outsourced is also very high.
--
Personally, I believe infrastructure procurements should be priced based on tangible deliverables.
Let's say we put out an RFP a for work package which amounts to : "New railway between Havelock and Glen Tay, built and maintained to Transport Canada standards, able to support train frequency of A with average speed B and with availability C, designed, financed, built and maintained for 30 years."
Apart from the small problem of TC absurdly not having published a Canadian equivalents of FRA class 6 or 7 in its 2021 track standards update, this makes for a straightforward and tightly specified job that it should be pretty hard to screw up.
The private sector bidder has:
- The incentive to design and build for cost effective long term maintenance.
- The ability to innovate and find the lowest cost yet durable construction methods
- Some freedom, subject to the Impact Assessment process, to choose tweaks to the alignment to deliver the design speed.
The Assistant Deputy Minister for HFR cities the new Champlain Bridge project as a P3 success story, although there are complexities: it was DBFOM to start with, and then the government decided to cancel tolling it, making it more like a DBFM and removing a lot of revenue risk from the consortium.
What will happen with a HFR DBFOM, according to the ADM, is that they do not expect the P3 consortium to include a general contractor or a rolling stock manufacturer, so it would subcontract such work packages anyway. However, the financing is bundled and the risk aggregated, including operations and revenue which brings in a whole menagerie of externalities over the which government still has more control over than the consortium, so the principle of "risk transfer" breaks down.
One of the risk factors is the regulatory framework for operations over Metrolinx, Exo, CN and CP infrastructure. The JPO report says nothing useful about this crucial issue. It needs a complete overhaul, or the new operator will be just as thoroughly hexed as VIA Rail is now. My thinking would be that the model of buying a 50% interest in a corridor, as used by Virginia and CSX, could be applied to tracks to and from the new HFR alignments. A revised form of TSA, with performance guarantees and phased capacity enhancement plans built in, might work elsewhere. CN and CP will insist upon managing the projects on their infrastructure, so third-party cost monitoring would have to be arranged in order to prevent a reprise of the Kingston Sub upgrade snafu. There's nothing a HFR consortium can do about track access that couldn't be done in the public sector.
Long term ridership and travel demand in the corridor is going to be more dependent on public policy than the operational details of HFR, assuming the stated travel times and frequencies are delivered. The only certainty is the public policy on issues like housing is going to have to change. How will the government handle road pricing or congestion charging once the gas tax is gone? What will immigration policy be in 2040? Will the integration with public transit to make complete journeys seamless happen? The consortium can not arrive at anything better than a wild-ass guess, even with good data the best of intentions. There's no "secret sauce" that a private proponent can bring to the table to do this better.
That's why franchising in the UK was already failing and being dismantled, even with shorter concession periods to predict for, and before the pandemic consigned everyone's ridership projections to the dumpster. At least in the UK, with multiple franchisees, the "operator of last resort" could take over underbid franchises and restructure them. Here, with a single concessionaire, they'd be "too big to fail" and that's very bad news for taxpayers because we keep all the downside risk while losing most of the upside.
What started as a fairly straightforward $4B plan (In my opinion. I have colleagues in Transport Action who thought it too large even then.) is now, two election cycles later, a ~$12B megaproject and not likely to happen before another election kills it... yet again. That's ridiculous and depressing. I owe a big thank you to the people who've convinced me over the last few weeks that Canada's passenger rail network is still worth fighting for.
Terry