It sure is, I'm really amazed at the speed here. This baby is completing one floor a week with ease. Did Casa go up this fast once it got past the above ground parking levels? I walk past here every day as it's on my dog walking route, I only passed Casa perhaps once or twice a week.
From what I've seen, the going rate of other projects is also 1 floor/week after underground levels and lobby are complete, as long as the floorplate is similar going all the way up and not huge (ie. larger than 100 x 100).
But it will still take them many more weeks/months to clad and finish up the interiors, so my rule of thumb has been to estimate 1 month per level once ground breaks.
When did X break ground + 44 months = completion date