I passed by the building yesterday and spoke with some of the workers. They said that they are presently pouring the 11th floor. The construction plan is to complete 2 floors per week.
So if my math is correct: 44 stories - 11 floors done = 33 floors / 2 per week = 17 weeks or so until the building tops out!
Woohoo, as a buyer I am looking forward to seeing the thing top up around the end of the summer.