Oh, okay, are you saying there’s a second notification because there’s a “1. Blah blah blah” and a “2. Blah blah blah” in the letter?
I have a similar email and interpreted the response (which I posted above) as being the total number of days they were adding as it is a single event, one(1) unavoidable delay.
Yeah, this was sent during the second wave of the pandemic and after which was about 6months after we received the first one you posted. However, we never received revised dates after the email in December 2020. Read point 5 and 6 in the letter I posted -
5. It is difficult at this stage to be certain if or how long the total delays may be and thus how the construction schedule for your Home will be affected.
6. As more information becomes available, we will keep you informed of developments.