I just went through the East Lofts thread and found a few progress milestones with dates for comparison's sake:
Sept 01, 2008 - Rebar starting to approach ground level.
Oct. 28, 2008 - Ground level floor slab is poured
Sept 05, 2009 - Building is topped out - crane is removed on this day.
Oct 24, 2009 - Cladding and windows are mostly complete
Nov 02, 2009 - Developers post detailed update (post # 327)
Jan 2010 - First occupancies begin.
Based on this it looks like at least 14-16 months from now (Sept 01, 2011) considering that only half the building is built to grade.
Sept 01, 2008 - Rebar starting to approach ground level.
Oct. 28, 2008 - Ground level floor slab is poured
Sept 05, 2009 - Building is topped out - crane is removed on this day.
Oct 24, 2009 - Cladding and windows are mostly complete
Nov 02, 2009 - Developers post detailed update (post # 327)
Jan 2010 - First occupancies begin.
Based on this it looks like at least 14-16 months from now (Sept 01, 2011) considering that only half the building is built to grade.