September 11, 2022. Posting these here as they are an Ontario Line Early Works / Prerequisite Project activity. In support of the upcoming closure of Queen Street for construction of the Queen and University and Queen and Yonge Street stations, the Adelaide streetcar tracks are to be reinstated between Charlotte and Victoria Streets. Work is now actively underway, with delivery and preparation of the rail to a staging area on Adelaide, between Brant Street and Spadina Avenue, where the two centre lanes have been closed and taken over for the project. Starting from the west, just west of Brant Street, working towards Spadina Avenue.
Rail sections of the delivery truck. Shorter sections, to fit on the trailer, and be able to get through city streets and corners.
Adelaide Street closed east of Brant Street, with the mobile crane in position.
Crane lifting a rail section for welding into longer, 'continuous welded rail' pieces
Assembled welded rail sections, ready for installation once the track bed has been prepared. Given that the track bed preparation work has not even been started, suspect that the rails will be staged here for quite a while.