| Date/Period | Roadway Access (vehicle, bicycle, pedestrian) |
| August 29 – September 3 | Closed |
| September 3 – September 17 | Open |
| September 17 – September 22 | Closed |
| September 23 – October 23 | Open |
| Bridge expected to return to full operation October 23. |
They're got a pretty fun looking model of the PlayPark at the CNE!
View attachment 592153
View attachment 592154
Fund Raising ongoing. See https://www.waterfrontoronto.ca/our-projects/PlayPark This model is usually at the WT offices on QQE.When is this supposed to be made?
Yes, the Don Roadway at the Commissioners St end is just about at the right level now - though I doubt it is ready for paving yet. It will be interesting to see how they link it to the planned extension of Polson St (or, more importantly, how Polson will cross the flood plain!)I was coming home from Peterborough this evening on The Gardiner and noticed that the Don Roadway is really prominent now and may be close to the height needed to pave. Will try to get pix as I am down there this week.
OPENS IN 2 minutes!! (Well, so Ports Toronto now says!)
Toronto (September 3, 2024) –
The Ship Channel Bridge (Cherry St. Bridge) roadway will be open to vehicle, bicycle and pedestrian traffic between 3:00 p.m. Tuesday, September 3 and 12:00 p.m. Thursday, September 5.
There has been another of the endless revisions to the repair schedule as crews proceed with ongoing critical repairs. As a result, the bridge will be closed between 12:00 p.m. Thursday, September 5 and 3:00 p.m., Friday September 6. It will reopen at 3:00 p.m. Friday, September 6 and is expected to remain open until 12:00 p.m. Tuesday, September 17, with a brief overnight closure on Tuesday, September 10.