drum118
Superstar
Mississauga South
As construction activities progress along the entire Hazel McCallion project, the people living and working in Mississauga South will notice some changes within their communities along Hurontario Street.- Acoustic fencing installed along the east side of Hurontario Street, just south of Mineola Road
- Crews are nearing the completion of underground Alectra upgrades at properties south of Mineola to Pinewood
- Later this summer, crews will return to string cables and connect the adjacent properties to the new underground Alectra service
- Temporary electrical service disruptions are expected and will be communicated to individual property owners/managers in advance.
- Traffic has shifted to the east side of Hurontario to accommodate road widening activities along the west side of Hurontario
- Road widening is currently progressing from Inglewood Drive in the south to Pinetree Way in the north, involving the removal of asphalt and concrete curbs, followed by excavation, curb preparation, concrete pour, and paving.
To safely accommodate these works, driveways for properties within this stretch will be intermittently and partially impacted for less than a total of four hours as activities progress from south to north over the next two months. Once the roadway has been widened, guideway construction in the area can begin later this year.
Eaglewood Bridge
Temporary traffic signals have been installed at the new Eaglewood Boulevard bridge, creating a new signalized intersection that will replace the current bridge and intersection at Inglewood Drive. Allowing for a better flow of east/west traffic to cross Hurontario Street and pass straight through at Eaglewood Boulevard.
The new Eaglewood bridge and intersection will also allow the tracks, once constructed later this year, to move from the centre of Hurontario Street to the new station at Port Credit along the west side of the road. This creates a safer environment for the future operation of light rail vehicles and for Hurontario traffic.
Mississauga Cooksville
Utility and Roadworks:
The relocation and installation of utilities is continuing in Cooksville. Stormwater catch basins are also currently being installed on the northwest corner of Hurontario Street and Queensway.New hydro (Alectra) poles are being installed throughout the area. During the installation, there will be partial short duration impacts to driveways. Telecommunication duct banks are being installed between Harborn Road and The Queensway.
Road Widening and Track Installation
- Road widening has started on the west side of Hurontario Street between Harborn Road and Dundas Street.
- Access will be maintained with the help of a flag person during temporary partial driveway closures.
Track installations are being planned at the intersections of:
- Matthews Gate
- Elm Drive
- Central Parkway
- The Queensway
Mississauga Centre
Utility and Road Works:
Track installation is ongoing in central Mississauga along Hurontario Street. A partial intersection closure at Elia Avenue/Kingsbridge Garden Circle and Hurontario Street is scheduled from March 25, 2024 to April 22, 2024. During this construction, east/west traffic and left turns will not be permitted at the intersection.Detours routes are available via Kingsbridge Garden Circle, Eglinton Avenue, Sorrento Drive and Elia Avenue. We encourage motorists to plan for delays.
Preparations are underway for the installation of the LRT stop at Robert Speck Parkway.
In the next three months, track works are expected to start the following intersections along Hurontario Street:
- Square One Drive
- Absolute Avenue
- Burnhamthorpe Road
Alectra duct banks, catch basins and overhead catenary poles are also being installed in the area
Progress on the Elevated Guideway
Piers are being installed and decks are going in for the elevated guideway near Hwy 403. This will be followed by electrical and track installations.Mississauga North
Guideway Construction:
All intersection work has been completed in Mississauga North. Track construction continues along the centre of Hurontario Street. Work has also started on the LRT station stops in north Mississauga.Crews are also working on installing the units that provide power to the Hazel McCallion Line, called traction power substations. Left hand turn restrictions remain in place at Britannia Road as crews work to connect the unit to the power grid.
Utility Works:
Dry and wet utility crews are completing punch list items and correcting deficiencies in the area with minimal impacts.
401 Overpass:
The 401 overpass is being widened to accommodate the LRT guideway. Crews are installing OCS pole bases. Guideway concrete work will follow.
Derry station stop canopy is now installed including the final decal work; residents can expect to see more canopy installations at stops throughout the Hurontario Street later this year.
Brampton South
- Crews are relocating and improving watermain and telecom utility lines prior to guideway installation
- Partial driveway closures are coming up for subgrade utility and roadworks
- Track installations are happening at the project’s maintenance facility
- Curb installations are happening north of Highway 407
With two additional lanes being built to accommodate the future north and southbound lanes, the bridge expansion will allow for the LRT trains to cross over Highway 407 ETR without delay and for vehicular traffic to remain smooth.
Crews have recently demolished the east side of the bridge and are pouring concrete to form the new barrier wall.
This work has been taking place overnight with temporary lane closures to minimize impacts to commuters.
The Operations, Maintenance and Storage Facility
The LRT project’s Operations, Maintenance and Storage Facility is bustling with activity, crews are working on the exterior of the building, including landscaping and track installation between the facility and Edwards Boulevard.
The interior of the building is nearing completion, with work ongoing to complete the control room.
|