Here's the formal pre-qualification for the first package of civil & utility works.
The scope of work includes: The major components of the civil infrastructure scope for Package 1 include the following:
• design, construction and commissioning of third-party infrastructure which will include the relocation of all underground utilities, both public and private.
• reconstruction of all roads, curbs, sidewalks, and hard/soft landscape areas disturbed by the Project,
• construction, replacement and rehabilitation of all structures and retaining walls necessary for the Project.
• reconstruction of Frid Street to accommodate the proposed run-in track, spanning from Main Street West to the Operations, Maintenance, and Storage Facility (OMSF) located at Chatham Street.
• conversion of existing one-way traffic on Main Street to future bi-directional configuration and changes to the relevant traffic pattern;
• interface with enabling works contractors engaged by the Owner, if any, for work including utility design and relocations;
• work affecting Ministry of Transportation (MTO) infrastructure will require the service provider(s) to be registered in MTO’s Registry Appraisal and Qualification System (RAQS) for engineering and construction contract administration, before undertaking the works; and
• additional works agreed during the Alliance Development Phase which provides value for money for the whole project