News   Dec 12, 2025
 695     0 
News   Dec 12, 2025
 1.6K     6 
News   Dec 12, 2025
 766     0 

Toronto Eglinton Line 5 | ?m | ?s | Metrolinx | Arcadis

Anyone have any updates or predictions on opening. I originally thought Ford would want to open it by election next June but that seems impossible at this point! Doesn't seem like we are going to get the whole line operational until end of 2023 at the earliest it seems.

I live on Eglinton on the above grade portion and have not seen trains being tested... I guess the testing has gotten delayed.
More likely they discovered "concerns" or "errors" that need to be "tweaked".
 
It does seem that the previous September 2020 and September 2021 timelines were disingenuous at best and actively misleading at worst. There's no way either of those was going to be met, underpinning delays and COVID or not. My guess for the line opening is late next year. Some stations are still pouring concrete, as people have pointed out. There's a tremendous amount of work that still needs to be done, and ML announcing Sept 2021 a while ago was ridiculous.
 
It does seem that the previous September 2020 and September 2021 timelines were disingenuous at best and actively misleading at worst. There's no way either of those was going to be met, underpinning delays and COVID or not. My guess for the line opening is late next year. Some stations are still pouring concrete, as people have pointed out. There's a tremendous amount of work that still needs to be done, and ML announcing Sept 2021 a while ago was ridiculous.
People can still use it if the landscaping is not done. Seen many a subdivision or condo development where people move in as they are still working on the project.
 
From my experience with the Crossrail project here in London - beware of substantial further delays, especially given that the rail + signalling isn't finished yet.

The moving block signalling for the tunnels combined with manual operation on the surface - ensuring that the "handshake" between the signalling systems works is super important - this caused the Muni Meltdown in San Francisco in 1998, and ensuring that 4 (yes, four!) digital signalling systems are all talking to each other and working correctly caused many delays in the Crossrail project.

That's before you get to other things off to the top of my head that could cause delays - especially when they are interdependent!
  • linking Line 5 to TTC Transit Control and any issues you find there,
  • ensuring all the CCTV cameras work and are pointed at the right things - OPTO cameras can very fiddly to get right!
  • getting all of the new ticket machines and fare gates fully working,
  • signing off fire safety certifications for significantly more Underground stations at once (when would be the last time that 14+ Underground stations opened all at once in Canada?),
  • proper substantive testing and trial operations of all of the new rolling stock over all of the line,
  • Hoping that contractors have not been lying through their teeth about contract progress so that Crosslinx pays them,
  • Hoping that lower level staff have been correctly passing bad news to their bosses about delays/issues
  • Getting Crosslinx, TTC, City and Metrolinx to correctly agree who's problem is who's - remember Ottawa's Confederation Line and who had the power of "final completion" signoff?
 
Has anyone been watching LRT train testing anywhere along the east line from Kennedy to Leslie? Any Videos of Dynamic Testing?

Nothing has been going on out my way (that I could see) for the past couple weeks. I am always out along Eglinton from Kennedy to Pharmacy.
 
Has anyone been watching LRT train testing anywhere along the east line from Kennedy to Leslie? Any Videos of Dynamic Testing?
I've gone multiple times looking but they seem to have been in storage at science centre pretty much since a week or two after they arrived.
I went along the entire Scarborough section today and most of the work on the tracks and stops seems done at this point, but they're still working on the streetscape and getting around is an absolute nightmare if you're on foot or biking.
 
I've gone multiple times looking but they seem to have been in storage at science centre pretty much since a week or two after they arrived.
I went along the entire Scarborough section today and most of the work on the tracks and stops seems done at this point, but they're still working on the streetscape and getting around is an absolute nightmare if you're on foot or biking.
It is interesting no one is working on the above grade as many sections are incomplete. For example I passed by wynford to warden and the rubber part is not installed on the tracks yet and also the stations seem to have a lot of work cosmetically at least to finish. I assume those workers moved to the underground portion to start installing those track works? just speculating but pretty disappointed with the lack of progress on the above grade section the last couple weeks.

Imagine an informal strike taking place lol
 
Part 1 of 3 taken at Fairbank station on July 9, 2021:

IMG_0889.jpg
IMG_0890.jpg
IMG_0891.jpg
IMG_0892.jpg
IMG_0893.jpg
IMG_0894.jpg
IMG_0895.jpg
IMG_0896.jpg
IMG_0897.jpg


They are all back side of the southeast entrance.
 
I've gone multiple times looking but they seem to have been in storage at science centre pretty much since a week or two after they arrived.
Nitpick: they're storing the cars in the tunnels west of Leslie, not at the Science Centre.

Until quite recently they were still doing some final work in a couple of locations along the line - for instance, there was a bit of remedial work required to the overhead at the Leslie portal, and the bridge over the West Don River only finished being waterproofed a week or two ago.

I had been told however that they had manged to slip out a do a bit of overnight testing in places, although as much as anything that was for checking clearances.

Dan
 
Nitpick: they're storing the cars in the tunnels west of Leslie, not at the Science Centre.

Until quite recently they were still doing some final work in a couple of locations along the line - for instance, there was a bit of remedial work required to the overhead at the Leslie portal, and the bridge over the West Don River only finished being waterproofed a week or two ago.

I had been told however that they had manged to slip out a do a bit of overnight testing in places, although as much as anything that was for checking clearances.

Dan
ah thanks didnt know that!
It is interesting no one is working on the above grade as many sections are incomplete. For example I passed by wynford to warden and the rubber part is not installed on the tracks yet and also the stations seem to have a lot of work cosmetically at least to finish. I assume those workers moved to the underground portion to start installing those track works? just speculating but pretty disappointed with the lack of progress on the above grade section the last couple weeks.

Imagine an informal strike taking place lol
I mean there were a tonne of workers just mostly working on the sidewalks and such. Still, quite a few doing works around the tracks and stations over by ionview and birchmount so maybe they're working their way westward
 

Back
Top