mdu
Active Member
I have a religion to introduce to you...Since when have things been orthodox in Russia
I have a religion to introduce to you...Since when have things been orthodox in Russia
Strangely enough, that was going through my head as well when I read that post!I have a religion to introduce to you...
That's not always possible as they usually use the completed tunnels to remove the dirt that is excavated by the TBM so having stations being built around that isn't always possible plus you also have the tunnel lining sections being delivered to the TBM as well.I don't know much about engineering, but I can confidently say that they could've built each station consecutively (after the TBM passes through the station box).
On the other hand, politicians keep getting in the way
That's why they should get 6 TBMs to dig for the Crosstown. This cuts down time. Use Cedarvale as the launch site instead so the TBM could both started at the same place for liner delivery and dirt removal. If they dug the launch shafts all at the same time, they could have bored all 3 segments (Black Creek to Cedarvale, Cedarvale to Eglinton and Brentcliffe to Eglinton) at the same time. It'll take about 12 to 15 months to complete, completing in 2013/14. Then they could build each station in 3-4 years time pegging the opening date in 2017/18.That's not always possible as they usually use the completed tunnels to remove the dirt that is excavated by the TBM so having stations being built around that isn't always possible plus you also have the tunnel lining sections being delivered to the TBM as well.
Time to put on my ex-TBM designer hat. For soft- or mixed-ground geology like Toronto, the tunnel pushes off the lining as it installs it. Push TBM forward to mine -> pull back propulsion cylinders to make room behind machine -> install next ring -> push off the new ring. The 'muck' either gets taken out of the tunnel in a train (temporary tracks) or a conveyor.Basically, yes. The vast majority of TBMs jack themselves through the tunnel they've bored by hydraulic pistons. In a lot of cases where the TBMs also install tunnel linings as part of their forward progress, they will push against these linings.
Dan
It's easy to criticise when I don't know what was buried down there... but..... I really question the decision to deep bore using TBM's for so much of the route.
Perhaps a TBM was needed for some portion, but was that really the right decision?
And now we have four more projects that are TBM based.... again, while necessary in some places, is that really the right decision throughout?
Too late to change for this project, but I wonder if there should have been some detached and critical thinking done before those next four projects were launched. If you don't study history, you repeat the same mistakes.
- Paul
A lot of projects now look just as much as how life will be lived during construction as afterwards. (Whether this is the right approach? I don't know.) That's why TBMs and mining have become much more prevalent.
The first section of the YUS and the B-D subways were built as cut-and-cover. On the B-D, they were lucky and were able to use a parallel street for much of the length to prevent having to basically shut down Bloor and Danforth for years. But on the southern section of the YUS that wasn't possible, so Yonge was basically impassible for 4 years.
In the case of Eglinton, would we be willing to have that be the case? Would it be allowable to have the street unusable for that length of time (or maybe even longer)?
And before anyone remarks that "it's basically unusable now".....there is still a lot of traffic able to use the street today, and the street is still fairly vibrant around midtown and out towards Oakwood. If the line was built as cut-and-cover, there is no guarantee that it would be possible to maintain 2 road lanes all of the way across (such as around Yonge).
Dan
B-D didn't use an existing street (well, it did on a few small sections), the vast majority of the line just expropriated 3-4 houses on every street to the north of Bloor and demolished them.A lot of projects now look just as much as how life will be lived during construction as afterwards. (Whether this is the right approach? I don't know.) That's why TBMs and mining have become much more prevalent.
The first section of the YUS and the B-D subways were built as cut-and-cover. On the B-D, they were lucky and were able to use a parallel street for much of the length to prevent having to basically shut down Bloor and Danforth for years. But on the southern section of the YUS that wasn't possible, so Yonge was basically impassible for 4 years.
In the case of Eglinton, would we be willing to have that be the case? Would it be allowable to have the street unusable for that length of time (or maybe even longer)?
And before anyone remarks that "it's basically unusable now".....there is still a lot of traffic able to use the street today, and the street is still fairly vibrant around midtown and out towards Oakwood. If the line was built as cut-and-cover, there is no guarantee that it would be possible to maintain 2 road lanes all of the way across (such as around Yonge).
Dan
How much disruption can we reduce by doing stacked cut and cover tunnels (1/2 the width, but probably 1.5x the construction time)?A lot of projects now look just as much as how life will be lived during construction as afterwards. (Whether this is the right approach? I don't know.) That's why TBMs and mining have become much more prevalent.
The first section of the YUS and the B-D subways were built as cut-and-cover. On the B-D, they were lucky and were able to use a parallel street for much of the length to prevent having to basically shut down Bloor and Danforth for years. But on the southern section of the YUS that wasn't possible, so Yonge was basically impassible for 4 years.
In the case of Eglinton, would we be willing to have that be the case? Would it be allowable to have the street unusable for that length of time (or maybe even longer)?
And before anyone remarks that "it's basically unusable now".....there is still a lot of traffic able to use the street today, and the street is still fairly vibrant around midtown and out towards Oakwood. If the line was built as cut-and-cover, there is no guarantee that it would be possible to maintain 2 road lanes all of the way across (such as around Yonge).
Dan