UGGGGGGGGGHHHHHHCut and cover will make for worse traffic during construction
Like you're technically not wrong, but consider the fact that C&C construction will also take a lot less time. Like it will be worse than Eglinton is right now, but consider the fact that Eglinton had to have the roads torn open and locked businesses out of much traffic for 6 or so years, namely because stations are quite deep, thus extending construction timelines. Meanwhile, I'm pretty sure the Cut and Cover BD extensions to Islington and Warden took like 2 years total to build.
In short, if its a lot of disruption over a short period of time, vs a medium yet significant amount of disruption over a long period of time, I'd take the former in a heartbeat.
ProbablyDoes this include knock out sections for longer trains?
1) Yonge Line suggests otherwise.Cut and cover may limit buildings that can be built on top of the line if it is not in the middle of an existing roadway.
2) It will probably be built in the middle of the roadway.