Oh heres a twist:
The Lease requires that, where the building constructed is damaged by any cause where over 50% of the building is unfit for the purpose of a museum and is not capable of repair/restoration within three years or where the Province fails to make available the funding to repair/restore within one year, both or either of the City and TRCA may terminate the lease with respect to their own lands. Where the lease is terminated, the City/TRCA can elect to either take possession of the buildings on the Site or require the Province restore the Site to its original condition at the expense of the Province
Also staff saying its not feasible to run the science center. it would require a full doubling of the entire arts budget just for the science center