Some work this morning on the north side.

194803


194804
 
From Cressy's newsletter:

King-Liberty Pedestrian Cycle Bridge Update

Construction of the King-Liberty bridge is well underway. It will provide a much-needed accessible connection for pedestrians and cyclists over the rail corridor between Western Battery Road and King Street West/Douro Street.

The steel bridge structure is currently being fabricated and painted at the contractor’s facility near Kitchener and is planned to be hoisted into place and installed over the weekend of September 14, 2019. Unfortunately, this is later than originally planned in order to minimize disruption in the community. Once the steel structure has been hoisted into place, the bridge’s concrete deck, glass, security systems, elevators, and electrical connections will be installed.

Although the full opening of the bridge is anticipated for spring of 2020, the City is working with its contractors to identify opportunities for an earlier partial opening for the community.
 
From Cressy's newsletter:

King-Liberty Pedestrian Cycle Bridge Update

Construction of the King-Liberty bridge is well underway. It will provide a much-needed accessible connection for pedestrians and cyclists over the rail corridor between Western Battery Road and King Street West/Douro Street.

The steel bridge structure is currently being fabricated and painted at the contractor’s facility near Kitchener and is planned to be hoisted into place and installed over the weekend of September 14, 2019. Unfortunately, this is later than originally planned in order to minimize disruption in the community. Once the steel structure has been hoisted into place, the bridge’s concrete deck, glass, security systems, elevators, and electrical connections will be installed.

Although the full opening of the bridge is anticipated for spring of 2020, the City is working with its contractors to identify opportunities for an earlier partial opening for the community.
Same update 2 posts before yours
 
Construction Update – August 30, 2019
September 3 to 16, 2019: Temporary Road Closure on Western Battery Road and Douro Street
September 13 to 16: Overnight and weekend

Construction of the King-Liberty Bridge is well underway and the bridge piers are now in place.
This September, the steel bridge structure will be hoisted into position and installed. In order to bring the large steel truss into place, work will take place overnight and require temporary relocation of on-street parking on some local streets. Local access for vehicles will be permitted. Thank you for your patience during this work.
Read more details about access, parking, and other impacts in the construction notice:
King Liberty bridge towers under construction(August 2019)

Bridge piers ready for truss


King Liberty Bridge Painted Truss

Bridge truss prior to installation

Once hoisted into place, installation of the bridge’s concrete deck, glass, security systems, elevators, and hydro connections will proceed.
The full opening of the bridge is anticipated for Spring of 2020 and the City is working with its contractors to identify opportunities for an earlier partial opening for the community.
 