Allandale25
Senior Member
^ technically reopen?
The platform is opening February 13th^ technically reopen?
Here is a shot of (kinda) Bayview Junction. No progress on installing the 3rd track yet. Could CN be waiting for the spring/summer to put it in?
That's exactly the case. The weather is too cold (maybe not specifically this year, but as a general rule in the winter), and the ground too frozen, to effectively do the earthworks required to prep the subgrade for the third track.
Dan
Would it be fair to say/guess that work should be completed by the summer, meaning that increased West Harbour service could follow in the early fall?
^ just out of curiosity couldn't Metrolinx ask or pay for the work to be contracted out to a company like PNR Railworks? Or are there certain internal CN requirements (like union rules) that require CN employees to do the work?
The new number 1 track for Weston Sub will be in place once the tunnel is done along with the new Eglinton GO/UPX station, Weston Station and at Bloor St as most of it is in place. One other area that may need tracks is north of King St to Dundas. There are 3 tracks to Bramalea today as before. Then you got the Woodbine station EA to be done before it will require track work as well building the station.It’s definitely encouraging to see these projects acknowledged with a little more specificity. They are all welcome.
I’m still wondering about “Ready, aim, aim, aim”.... completing TPAPs is a necessary step down the road, but not a guarantee. How do we know that they will lead to action? Some of these items are stepping ahead of other things that were studied/announced in the past. Are those items not proceeding ? Has Ml cooled its interest in those other things?
One example is the 401/409 tunnel....has all the diligence been assembled to complete the whole fourth track from Strachan to Bramalea? Has all the procurement been completed for that work? Or will we see the tunnel completed only to find that some other study or consultation is still needed a couple miles down the line, and track wont’t be added until more studies are undertaken?
Why are things like the work to add sidings west of Georgetown not included in the description of what’s going on? What about Georgetown to Bramalea - do we have a design agreed to? Will there be new TPAPs before this work can begin?
I’m hopeful that the public meetings will speak to these questions. I’m encouraged by the things that have reached active construction, but one can’t always trust ML to remember all the work they previously said was about to begin.
- Paul
Stouffville double track has been done in many location, but other areas still needs to be done. Agincourt, Milliken and Kennedy are being worked on and it will be 2021 before these stations are double track. How to double track from Kennedy to the Lakeshore line is unknown at this time.