Danforth Line 2 Scarborough Subway Extension

November 2022 Market Update release earlier today. Relevant SSE information see below:

DPA Development Phase Agreement expected to be announced by the end of this month.

Project Scarborough Subway Extension – Stations, Rail, and Systems
Project Phase Active Procurement
Model Progressive DB (target price)
PDC/TA Procurement N/A
Issue RFQ September 2021
Issue RFP February 2022 (Dev. Partner)
Contract Execution DPA: Nov 2022 AND PA: Jul – Sep 2024
Design & Construction Cost $2B - $4B

Source - https://www.infrastructureontario.c...et_Update/Market Update_11212022_FINAL_EN.pdf
 
Today:

20221126_144901.jpg
 
News today:

 
Shouldn't there be platform screen doors? Again, not in the budget. Same old, same old.
there may not be any in the rendering, but it's clearly been designed for them with the low overhang immediately over the subway trains.

Also, It's interesting to see subway design return to a more basic, restrained design pattern again following the TYSSE. Simple stations, similar to the last PC-led subway project, the Sheppard line.

It is interesting in that the PCs do seem willing to spend money in a few key spots like Exhibition station, but you see a real drive to build simple stations to save costs. The OL and Scarborough station renderings we have seen generally seem quite restrained compared to even the Crosstown underground stations.
 