November 2022 Market Update release earlier today. Relevant SSE information see below:
DPA Development Phase Agreement expected to be announced by the end of this month.
Project Scarborough Subway Extension – Stations, Rail, and Systems
Project Phase Active Procurement
Model Progressive DB (target price)
PDC/TA Procurement N/A
Issue RFQ September 2021
Issue RFP February 2022 (Dev. Partner)
Contract Execution DPA: Nov 2022 AND PA: Jul – Sep 2024
Design & Construction Cost $2B - $4B
Source - https://www.infrastructureontario.c...et_Update/Market Update_11212022_FINAL_EN.pdf
DPA Development Phase Agreement expected to be announced by the end of this month.
Project Scarborough Subway Extension – Stations, Rail, and Systems
Project Phase Active Procurement
Model Progressive DB (target price)
PDC/TA Procurement N/A
Issue RFQ September 2021
Issue RFP February 2022 (Dev. Partner)
Contract Execution DPA: Nov 2022 AND PA: Jul – Sep 2024
Design & Construction Cost $2B - $4B
Source - https://www.infrastructureontario.c...et_Update/Market Update_11212022_FINAL_EN.pdf