Valera Construction Update – February 2022
There are lots of exciting things happening at Valera! Since our last construction update, a lot has been done at Valera.
Building A
- Framing is complete on Level 7 and started on Level 8
- Drywall is complete up to Level 5
- Kitchen and flooring installation has begun on Level 2
Building B
- Windows are fully installed on Level 4 and started on Level 5
- Hallway framing to begin shortly
Townhomes
- Roof framed in Block 1, drywall and stucco underway in Block 2
- Drywall and taping ongoing in Block 3, plumbing rough-in started in Block 4
- All units being framed in Block 5, foundation walls being constructed in Block 6
- HVAC and electrical underway and stipple, trim, and railings install getting started in Block 7
As the weather thaws and spring rolls in, we are eager to keep the progress moving toward getting all units drywalled and finishes started.