This been on my due list and finally got around shooting it today. This is only a few of the 90 I shot for the area. No idea when the rest will be uploaded to by site, but these are not fix or tag
The new shift lane is mostly paved and strip except where the new QEW off/on connection is to go in as well the new south service road connection by Burger King. The curb for the new new south service road is pour with the road being graded so it can be pave.
Construction traffic lights being install at Sherway Dr and Dixie.
Rebar for the centre columns for the QEW are in place and waiting for forming that is sitting on the north side of the north pier support being form.
.
If there is a thread, them merger this with it.
This been on my due list and finally got around shooting it today. This is only a few of the 90 I shot for the area. No idea when the rest will be uploaded to by site, but these are not fix or tag
The new shift lane is mostly paved and strip except where the new QEW off/on connection is to go in as well the new south service road connection by Burger King. The curb for the new new south service road is pour with the road being graded so it can be pave.
Construction traffic lights being install at Sherway Dr and Dixie.
Rebar for the centre columns for the QEW are in place and waiting for forming that is sitting on the north side of the north pier support being form.