News   Apr 02, 2026
 2K     2 
News   Apr 02, 2026
 1K     0 
News   Apr 02, 2026
 2.4K     2 

GO Transit: Construction Projects (Metrolinx, various)

Going to be fun to watch them tie in this new 4th track where it meets the Barrie Line in the south. Some interesting construction picture opportunities. cc @crs1026
id take that with a heavy grain of salt. they laid down many sections of track on the stoufville line and then they abandoned them indefinitely. its still sitting there not fully connected.
 
id take that with a heavy grain of salt. they laid down many sections of track on the stoufville line and then they abandoned them indefinitely. its still sitting there not fully connected.
Also refer to how long they piled ballast for the second track through Guelph, and installed track at Guelph Platform 2 without tamping.
 
So durability
Longevity
Stuff like that...

Is it a quicker install? smoother ride? Quieter?
Smoother, stabler (with regular trackbed maintenance, which we don't generally have), quieter, longer-lasting, able to hold higher speeds, etc.

But wood and creosote are cheaper and Canada has a lot of it (and our trains don't move fast enough to make this an issue), so here we are.
 
Every single one except capital cost (and even that is debatable given the lifespan of a concrete tie vs wood).
Not quite.

Concrete ties have a longer theoretical lifespan, it's true. And they generally require less ongoing maintenance, as they are heavier and thus resist movement from the passing of trains much better.

But they are more expensive to purchase, as you point out. They are more expensive in terms of maintenance as well, as machinery is required for their installation or replacement - a 3-man crew can replace many wooden ties in a day with nothing more than hand tools.

And because concrete ties are much more rigid than wooden ties, they transmit more vibration to the ground and trains, which needs to be mitigated with special measures such as rubberized vibration mats. Another cost to endure.

Another issue, which is honestly a lot more rare but has proven to be a thing - concrete ties can fail if they are not made properly. MBTA and Amtrak have been replacing hundreds of thousands of concrete ties over the past 10 years because of this.

In high-use areas, yes concrete ties generally win out due to their reduced maintenance requirements. Cost reduction over their lifespan is a bit of a trickier thing to calculate, as there are many places where they are used on CN and CP solely to reduce the maintenance requirements, but are scheduled to be replaced in a similar manner to wooden ties.

Dan
 
Producing concrete ties also emits a lot of carbon dioxide. Remember when Canadians still cared about that?

True, but dead harvested trees don't cleanse carbon, lumbering is intrusive, and creosote is nasty stuff, especially if ties are burned at end of life.

The comparisons being made were on a different and more direct level, and more general environmental issues while valid are a different discussion that needs to be scoped appropriately.

- Paul
 
Last edited:
so what happened on the stoufville line from this weekend's shutdown? any meaningful progress on the line?
 
so what happened on the stoufville line from this weekend's shutdown? any meaningful progress on the line?

I didn’t see any new track laid this morning. I’m unsure if it’s a cognitive bias where I’m looking for changes that didn’t actually occur, but ballast north of Milliken station is a different colour (light vs. dark grey). Perhaps there was some preparatory work done ahead of the November construction closure.

The advertisement Metrolinx released on Facebook and YouTube stated they were “fixing and repairing” track this weekend, but I don’t want to overweight the script of an advert from the communications team.

I believe the weekend was to perform maintenance on the newly activated western track between Kennedy and Agincourt. The track and ballast appears “dusty” suggesting there was work done to it before it’s brought into service. Also, there was two pieces of small equipment left on the “shoulder” of the rail corridor.

The railroad equipment that was formerly stored on the western track at Lawrence SRT station is no longer there. Update: The equipment is being stored on the unused eastern track north of Milliken station.

Other updates

Finch-Kennedy Grade Separation
Piling is about to begin.

LSE Corridor
It may be cognitive bias (again), but the t-wall construction to rebuild the berm seems to be progressing at a quicker pace than last year.

However, I don’t see how the third (or fourth) tracks will fit between USRC and LSE corridor until East Harbour is complete. If additional tracks aren’t operational until the Queen/Dundas/Logan bridges is there capacity to increase service on the LSE and Stouffville lines?
 
Last edited:
I didn’t see any new track laid this morning. I’m unsure if it’s a cognitive bias where I’m looking for changes that didn’t actually occur, but ballast north of Milliken station is a different colour (light vs. dark grey). Perhaps there was some preparatory work done ahead of the November construction closure.

The advertisement Metrolinx released on Facebook and YouTube stated they were “fixing and repairing” track this weekend, but I don’t want to overweight the script of an advert from the communications team.

I believe the weekend was to perform maintenance on the newly activated western track between Kennedy and Agincourt. The track and ballast appears “dusty” suggesting there was work done to it before it’s brought into service. Also, there was two pieces of small equipment left on the “shoulder” of the rail corridor.

The railroad equipment that was formerly stored on the western track at Lawrence SRT station is no longer there.

Other updates

Finch-Kennedy Grade Separation
Piling is about to begin.

LSE Corridor
It may be cognitive bias, but the t-wall construction to rebuild the berm seems to be progressing at a quicker pace than last year.

However, I don’t see how the third (or fourth) tracks will fit between USRC and LSE corridor until East Harbour is complete. If additional tracks aren’t operational until the Queen/Dundas/Logan bridges is there capacity to increase service on the LSE and Stouffville lines?
i did see the yellow track machinery has moved north of milliken. i was hoping theyd make the connection to the station since they already have premade sections just ready to go for months.
 
i did see the yellow track machinery has moved north of milliken. i was hoping theyd make the connection to the station since they already have premade sections just ready to go for months.
I just passed the equipment on my commute home. I wrote my reply too early!

Perhaps overnight work can be done for Milliken station rather than requiring a weekend closure given there isn’t one scheduled until November.
 

Back
Top