I read Steve Munro's post, and more than a project off the rails, it put me in mind of a civilization in collapse. In 2007 it was supposed to cost half a billion and take 4 years to build. After 15 years of progress it hasn't been started and will now cost five times as much and take nearly 3 times as long. Longer than REM, both phases of the Ottawa system, longer than the Chunnel I think. And there's still no funding plan. It. Is. A. Three. Kilometer. Streetcar.
I do love a civilization collapse, but to be fair, this is what Steve Munro says:
- Union Station Loop, $932 million.
- Remainder of project except Cherry North, $1.3 billion. Includes East and West portals on Queens Quay, Queens Quay Station, Yonge Slip infill, Queens Quay East track from Bay to Cherry, Cherry Street south, Commissioners Street and Villiers Loop.
- Cherry North connection to Distillery District, $337 million, to be completed as a separate future phase.
For the record, I've always thought the Union Station Loop was bad value for money ($932 million for a 500m tunnel) and I agree it should be put off.
I'd prefer to see Cherry North get done as part of the first phase.