The 2nd crane was in the process of going up at 4pm in the south-west cor. Most was up with the boom laying on the Dunbloor road. Couldn't get the camera out of the bag to try to catch a shot from the westbound bus.
Construction continues on Village Gate West in Toronto October 6, 2009
WILLIAM CONWAY/PROGRESS PHOTOGRAPHY
Progress is being made on the Village Gate West III condominium/rental project in Toronto. Owner/developer Concert Properties Ltd. and general contractor Deltera Inc. began the two-tower, 501-unit project in spring 2009.
The project also includes 12 townhomes and four levels of underground parking linking both towers. The project was designed by IBI Group Page + Steele Inc. Consultants are: Jablonsky, Ast and Partners (structural); M.V. Shore Associates (1993) Ltd. (mechanical/electrical).
Subcontractors include: Magine Contractors (excavation); Rumble Foundations (Ontario) Ltd.; Forma-con (precast); Mega City Tile; Hilton (painting); Stirling Carpet; Leader (mechanical); Cooltech Services Ltd.; Nortown Electrical Contractors Associates; and ThyssenKrupp Elevator Ltd.
I live next to this site at 11 Dunbloor and have been taking pictures and Video as the contruction has progressed. I will have to upload them to my Photobucket account and share here