Article from CBC News on the status of the PED project (basically no news at all). Not killed, but not approved.
The only bit of interest to me was:
Yes, some of us have questioned those estimates, which are extremely high.
Again, I want to note problems with the ways in which the TTC designs and manages project files.
In this case, they hired a third party consultant to synthesize all the info out there on PED types/options/costs, and to incorporate any TTC specific info they could and lay out a plan forward.
Fine, I suppose.
**
But there is a very high degree of uncertainty here, because the TTC has no experience building these, hasn't actually decided how it would manage partial or full station closures to carry out the work, has pushed them largely off into the future (requiring inflation estimates), and hasn't actually contracted with a company that has actually built these before, as retrofits.
**
My recommendation:
1) The commissioned report was correct to suggest a pilot station and then maybe 2-3 more where types of installation may vary. Good. Don't worry about the full cost right now, bite it off in chunks.
2) Hire a team with experience doing this work; and get the project to 100% design before tendering construction. Settle early on, on how to manage any closure issues.
3) Keep those short by turning the usual tender on its head. Short closure is a tender requirement and the on-site worker count must be maximized. Two weeks tops. During the work period, you shut down trains early through the station, and completely on weekends.
4) Use the pilots to inform the long term cost.
5) Prioritize stations with suicide and intrusion issues. If you fixed the most problematic dozen you likely fix 80% of the problems.
6) Get on with it, the re-study of the studies consumes money and staff time and just adds inflation to thee next estimate.
For those discussing where else retrofits of PEDS have been done.....its a good sized list (from the article linked above)