Toronto Via Bloor | 138.37m | 46s | Tridel | a—A

A short video and a screenshot:


188679
 
Yup a 1-1/2 year to get here
You think this is slow? Take a look at Rosedale on Bloor, or the condo at Wellesley and Church. Almost 5 months since they installed the crane, and the only things happening are some forms for the lowest underground level on a site that’s less than 1/3 the size of this.
 
Last edited:
Report from Tridel:

Installation of hoist elevators for each tower is anticipated in early 2020
Precast cladding and window installations is anticipated to begin in early 2020
Interior finishing of your home is anticipated to start in the Summer of 2020
 