For whatever it’s worth ………
I spoke with Domenic (VP), he said come August the progression will be a lot more visible and quicker. They held work on the west side, and focusing on the east side, still getting over hurdles regarding the hole and soil. This is the 20% of the work that is taking up 80% of the time. Until the hole and soil has been fully serviced and prepped, and the pillars put up, the more visible work re construction cannot commence. Once this has been done, the construction we want to see happening will begin.
We discussed the construction workers attesting not being paid. He said the workers would not be privy to such information and it makes no sense.
He also mentioned they are fully committed to completing the project because of the invested time and money into the project, and really aiming for late 2024, as per the last update.