innsertnamehere
Superstar
well it is behind schedule, but thats because of the death not because of this. York U has been problems since day 1 on this project, and ironically it is probably the most important station on the line.
Would it? Looking at 407 Station draft plans, the station is about 180 metres long and 20 metres wide. If the water is a foot deep you've got about 1,100 m³ of water.Ellis Don is in the hizzizz at York U. There are 3 trucks pumping away. At this rate, I have to say it looks like it's gonna take some time.
And, yeah, I'm curious where the heck they put the water..
I'd be surprised if they didn't pump 24/7. But even 3 weeks doesn't seem like a terrible amount of time. Presumably they have a date when they were planning to start work in the pit. They simply have to schedule to start pumping in advance, so it's completed in time.It's very hard to get a sense of the depth because I was like 5 stories above the site and the pit must be another 3-4 stories deep and it's just a big pit....but there is no way that's only one foot deep. Is it 10 feet? 4 feet? 15 feet? I really can't say without a wee person or something else down there to offer some scale but I think it's in the 5-10 range, if I had to guess. Even if it's only 5 feet, that takes your estimate up to 15 8-hour days, which is three weeks (unless they're going overtime, which I'd doubt, but who knows?).
its not going to be ready for the pan ams, its been delayed a year because of the death.
It was never scheduled to be ready for the Pan Am games. The opening was late 2015 when they started construction, and when the Pan Am games bid was done. If you look at the bid book for the Pan Am games, not only is there no mention of this extension being open for the games - there were no events planned at York.its not going to be ready for the pan ams, its been delayed a year because of the death.