Toronto Time and Space Condos | 101.8m | 29s | Pemberton | Wallman Architects

March 17
40469566243_9b4fd8850c_b.jpg

47435379791_72c585d675_b.jpg

40469570233_14f15df00a_b.jpg

47435383911_cc5e3eb0c1_b.jpg

47435384431_754b3ff2dd_b.jpg

47435384871_244db51212_b.jpg

33559302368_be35004a1c_b.jpg

47435390211_0d4c1edd5d_b.jpg

46520273685_96f36392aa_b.jpg

46520274685_e5227d5f9c_b.jpg

46520277065_8ddbf41ea0_b.jpg

46520277795_89f5dd1203_b.jpg

46712362234_4e680aa636_b.jpg

32493610047_06976c85d8_b.jpg

32493610047_06976c85d8_b.jpg
it's still in the same condition as last year hahah
 
http://pembertongroup.com/time-and-space-community/construction-update/ notices Pembertong group website update the construction update, it looks they plan to finish the construction around Jan 2023.

Under construction management plan tab, it is in stage one now.
===========================================================================

  • Stage one: This will involve temporary chain link fence comes with screen to allow for internal shoring drilling as the installation of a permanent plywood hoarding will impede heavy equipment at the perimeter. In addition to the temporary fence, rolling scaffold overhead protection will be used on the sidewalks with pedestrian control personnel stationed at the rolling scaffolding when required.
Start: August 2018 End: May 2019

  • Stage two: Upon shoring drilling completion and prior to bulk excavation start the temporary chain link fence will be replaced with plywood hoarding and overhead protection at the perimeter of the site. The estimated date for delivery of public art on hoarding will take place post hoarding and overhead protection completion and as approved by local Councillor.

Start: April 15, 2019 End: September 2022
  • Stage three: Upon completion of the all exterior assemblies and prior to streetscape construction the plywood hoarding will be removed and a temporary fence provided.
Start: September 2022 End: January 2023

All gates will be locked during hours where no construction activity is occurring. Appropriate signage will be installed to ensure that the safety of pedestrians, cyclists and motorists is considered at all times. Adjacent sidewalks with overhead protection will have appropriate lighting to ensure adequate visibility at all times of the day and night.
 
I live just to the north of this, and my very nice lake view will disappear when this project gets up to 16 storeys. I will be happy to trade excellent photos of the work site for any other information on its progress.
 
I live just to the north of this, and my very nice lake view will disappear when this project gets up to 16 storeys. I will be happy to trade excellent photos of the work site for any other information on its progress.
That would be a great idea if you can post photos from above.
 

Back
Top