November 5. First forms on the west side of the office tower have now moved up to start work on the 31st floor.

Cycle times per floor over the past months since early May have been:

Date.................Floor.........Days
May 1................19................-
May 28..............20................27
June 12.............21................15
June 25.............22................13
July 10...............23................15
July 24...............24................14
August 10.........25................18 (Includes the August long holiday weekend)
August 21.........26................11
Sept. 3................27................13
Sept. 21..............28...............18 (Includes the Labour Day holiday long weekend)
October 9...........29...............18
October 23........30...............14 (Includes the Thanksgiving Day holiday long weekend)
November 5......31...............13

20201105_155453.jpg
 

AHK

Senior Member
Member Bio
Joined
Jan 12, 2010
Messages
1,310
Reaction score
3,135
Friday, November 6 - three photos from the south side of The Well. First, an overview of the entire site from the south. Second, the Office Tower, showing the final setback for the topmost floors. Third photo - installation of the construction hoist for the south-east residential tower (Building 6) is underway.