I expect that all remaining non-maintenance floors will be completed at about one week per floor. (barring unforeseen circumstances.Hmm I hope their labor saving climbing rig will have make it faster than that. That in addition to the preassembled rebar supercolumns. Since at 2 weeks/floor, and 3 weeks/maintenance section, would put topping out at year end 2025, assuming no other delays.
A normal 200m+ condo is about 1 week per floor from what I understand. The One is obviously more complex, with more concrete, etc.,