Dear Purchaser:
We and would like to provide purchasers at The Ninety with a project update:
We have completed the demolition of the existing building on the south lands (the Climbing Academy building) and prepared the site for construction with the removal of trees, site services, installation of safety fencing etc.
We will now begin the excavation and shoring of the site, which will involve excavating down 4 parking levels into the ground. This stage of the construction process will take approximately 4 months to complete. We will then begin to pour concrete in order to form the garage and then the above grade building structure.
This summer we faced an unfortunate delay to the project. In working with our neighbours to the south (Broadview Lofts), we had designed a tie-back shoring system along the south side of the excavation. At the last minute, the neighbours reneged on the proposed agreement and we had to redesign the shoring system using rakers and resubmit the alternate design to the City for permit. This also required the structural redesign of the building on the south face. We are pleased to say that we have redesigned the shoring system and expect to obtain approvals shortly. We have re-tendered the shoring and excavation contracts and expect to re-mobilize and begin this work in September. As we can now resume construction activities, we will be able to refine our construction schedule. We will provide a further update on the schedule this fall once we are better able to define completion dates. We cannot provide a revised occupancy date at this time, however, the three month delay noted above probably means a three month further delay to occupancy. Over the next month or so we will look for ways of regaining schedule and providing you with a more certain date.