AlbertC
Superstar
Nov 28, 2020
Are you saying it's going to continue accelerating so by this time next year we'll have the next supertall?!This thread started in 2012; so we're about 9 years on...........
It took about 6 years to get a shovel in the ground.
It took 1 year, 8 months from the arrival of shoring to the arrival of the crane.
4-5 months to reach grade
About 2 months to get the 1st floor up I think, based on the pics.
Now we're up at the 7th floor roughly 4 months later.
Glad to see the pace has accelerated!
At the current rate, we should be topped out by the end of summer and substantial completion by year end.