Though the piling etc has been occupying the sidewalks for several weeks the official permission was only given by TEYCC on Tuesday. The Staff Report ( https://www.toronto.ca/legdocs/mmis/2018/te/bgrd/backgroundfile-110118.pdf ) gives some timelines:
Construction of the development will be undertaken in several phases. Major construction activities and associated timeline for the development are described below:
• Excavation and shoring: September 2017 to May 2018 (progressing);
• Below grade construction: May 2018 to August 2018;
• Above-grade construction: August 2018 to April 2021.
Construction of the development will be undertaken in several phases. Major construction activities and associated timeline for the development are described below:
• Excavation and shoring: September 2017 to May 2018 (progressing);
• Below grade construction: May 2018 to August 2018;
• Above-grade construction: August 2018 to April 2021.