From Ryerson Builds:
The tender for shoring and excavation was closed on January 16th and the remaining tender packages for various building trades (e.g., electrical and plumbing contractors) are being prepared by Ellis Don. These tenders will be posted throughout 2012.
The architectural team is currently reviewing cost estimates from Ellis Don and Marshall Murray (Quantity Surveyor) on various construction components. This is a quality assurance process to ensure the estimates are aligned.
Ellis Don is scheduled to take possession of the site on February 1st and should have the construction hoarding (installing plywood around the perimeter) installed by February 16th
http://www.ryerson.ca/ryersonbuilds/studentlearn.html
AoD
The tender for shoring and excavation was closed on January 16th and the remaining tender packages for various building trades (e.g., electrical and plumbing contractors) are being prepared by Ellis Don. These tenders will be posted throughout 2012.
The architectural team is currently reviewing cost estimates from Ellis Don and Marshall Murray (Quantity Surveyor) on various construction components. This is a quality assurance process to ensure the estimates are aligned.
Ellis Don is scheduled to take possession of the site on February 1st and should have the construction hoarding (installing plywood around the perimeter) installed by February 16th
http://www.ryerson.ca/ryersonbuilds/studentlearn.html
AoD