They have to install the entire "table top" steel and carry out all of the field welding at the node-to-pipe joints before they can fill the legs with concrete, as the unbalanced weight that results as each leg is filled from the base up 70-feet would cause some lateral movement if the steel diaphragm wasn't complete. I'll try to remember to post when the concrete filling is taking place...