reinventingthewheel
Active Member
Couple screens from the March 20 Virtual Info Session (available on youtube)
Piling is expected at a rate of 6 piles per day, with each one requiring 2 cement trucks to fill, quite the deep excavation! Trucks will approach north from Sherbourne then exit via Queen and turn left on Jarvis,
Piling is expected at a rate of 6 piles per day, with each one requiring 2 cement trucks to fill, quite the deep excavation! Trucks will approach north from Sherbourne then exit via Queen and turn left on Jarvis,