Toronto Ontario Line: Exhibition Station | ?m | ?s | Metrolinx | HDR

Is it too much to ask the PR flacks to convert all their measurements to the same system of measurement? And since I did the math, 48" is approximately 1220 cm.
Some of us don't really think about it...we just go back and forth between the two. I agree that the writer was lazy but, since it's so upsetting...I did the math...6.5 meters is around 21 feet.
 
Exhibition_-_Notice_of_Pile_Drilling-images-0.jpg
Exhibition_-_Notice_of_Pile_Drilling-images-1.jpg
 
Made a visit to the new/shifted Eastbound platform today.

Starting with the now blocked off West end of the platform, next to the entrance from the Ex/ped tunnel.

Z8P_0233.jpg


Walking West from the start of the new section.
Z8P_0238.jpg
Z8P_0242.jpg


Looking back West to compare the new accessible area to the one on the Westbound platform.
Z8P_0244.jpg


Going East again.
Z8P_0246.jpg
Z8P_0247.jpg


You can see the newly installed hoarding around the portal site, which will begin piling work later this month.
Z8P_0248.jpg


Looking back West from the new Eastern edge.
Z8P_0250.jpg
 
They've finally started to install the top and bottom of the cladding for the ped bridge staircases.

Z8P_2848.jpg
Z8P_2852.jpg


Moving East, here's an arial of the now closed off site for the future portal. Piling coming soon.
DJI_20240613151413_0022_D-2.jpg



And all the way West for an arial shot of the recently dug hole leading to a new utility tunnel under the tracks.

DJI_20240613151532_0023_D-2.jpg
 