After months of no progress, work has started back up on the (south) platform 4 extension for shifting to the east to match the (north) platform 1.
Also, work is progressing on the track 2 realignment with ballasts now laid for the new track location.
And work continues on the pedestrian bridge with roofing over the stairwell for platform 1.
Finally, some concrete was being poured in a recently dug hole at the former 2-20 Atlantic Ave site.

20240314_145107.jpg
20240314_145235.jpg
20240314_145453.jpg
20240314_145556.jpg
 
Closer look of shifted platform 4 being built out.

The station will be closed this weekend to allow for track relocation.


20240320_140532 (1).jpg
20240320_140750.jpg
Screenshot 2024-03-20 154406.png
 
About half of the new track 2 has been laid ahead of this weekend's work.

I made an edit of both images with the current track 2 removed to give a sense of the space that is will be left for the new platform that will service track 2 & 3 at the new station.

20240322_154910.jpg
20240322_155039.jpg

20240322_154910 copy.jpg


20240322_155039 copy.jpg
 
The station was a hive of activity today on the East and West end of the station as they work to move track 2 next to the new track 1.

First 3 shots are from the East side of the station, followed by the West end as seen from the Dufferin bridge, then finally a couple shots of the area where they demo'd the warehouses and started piling in the tail/storage track area for the OL. I'm wishing I thought to walk to this area before when the demo was taking place, but better late than never! This will hopefully be a vantage point anyone can continue to access as work continues.

20240323_141350.jpg
20240323_141458.jpg
20240323_141636.jpg
20240323_142646.jpg
20240323_143543.jpg
20240323_143629.jpg
 
With the re-alignment of track 2 complete, a new trench is being built at the foot of Atlantic for hydro to connect to the new station (3 weeks of work).

Photo 1 of the ripped up Atlantic Ave, Photo 2 is from the foot of Jefferson looking in towards where the Liberty New Street will be.

20240325_183527.jpg
20240325_183941 (2).jpg
metrolinx-hydro-work-1.jpg
metrolinx-hydro-work-2.jpg
 
Apr 8, 2024

Atlantic Ave looking south.

8A7FCFF2-6B4C-4C06-AAE4-4866EDB04C0E.png


Before demolition capture - Google

64A09A4A-4D90-4770-9C9A-ECAC3186DE9D.png


Post demolition.

81300A98-DB98-4856-B8A0-E3111820A598_1_201_a.jpeg



0BC8DBE6-F4F4-4E20-AB73-75D56BC17A74_1_201_a.jpeg



64A7C32D-7622-4693-B1A2-026E0A15794A_1_201_a.jpeg


Looking east.

30A9D962-82AD-42A4-AE15-B3D9B23DCF71_1_201_a.jpeg



1AC5D95B-346E-431B-8236-D12D21457246_1_201_a.jpeg



29822355-DF8E-4CC5-BE14-5BBF47A32D94_1_201_a.jpeg


Looking north across the tracks.

966A9C3F-BF37-4AB8-98F5-8C1F8EC3C54C_1_201_a.jpeg



7E081B99-48F5-4400-84E3-D62263F39E60_1_201_a.jpeg


Heavy clouds, but... did get the following of the solar eclipse.

STxTwQW.jpg
 
Last edited:
Cladding is coming along on the North Tunnel Headhouse. According to the architectural documents, it will be a permanent structure with Liberty New Street running right next to it. However, it looks as though the current existing tunnel headhouse that leads to and from the north go platform (#1) will be taken out, making the tunnel only useful for people needing to get through to the other side without entering the paid zone (concourse above tracks).

20240410_152745.jpg
20240410_152814.jpg

Screenshot 2024-04-11 114156.png

Screenshot 2024-04-11 112727.png
 
Last edited:
Got a progress update on the Platform 4 shift/extension thanks to the the ped bridge being open today for the TFC game. Looks like a couple weeks to a month's worth of work left based on the rate they've be going.

Also got some close up shots of the north tunnel headhouse.