Toronto Ontario Line 3 | ?m | ?s

So it’s likely to be above ground west of Bathurst and would be more useful north of the Gardiner, but will the Liberty Villagers object to having it cut through neighbourhoods.
 
If the Liberals before, or David Miller, or City Council when they took the transit file away from Ford, actually prioritized the DRL - then the station design would have been known.

I think it was way too late for DRL when they took the transit file away from Ford. Funding for DRL wasn't there, so they would have to cancel both the Ford's plans and the previous Transit City lines, and funnel all funds towards DRL. Not a chance anyone would vote for that.

Furthermore, the Crosstown was under construction; and the SRT required some form of replacement. Subtract those two, and the remaining funding was way too puny for even the most basic version of DRL.
 
I suspect the Province is eyeing something like #1 (red). Queen to Bathurst to Front under Fort York to station at CNE streetcar loop.
An alternative I could conceive of is #2 (orange). Quuen to Strachan to Fleet to Princes' to station near BMO Field.
The desire to not cut transit lines under building would preclude a lot of other choices.
View attachment 181406

Is a tunnel boring machine capable of making such tight turns?
 
One of a number of examinations of the plan. Again, the reference is to what was to be the *City's DRL plan*. It was to only cross the Don at one point!

The issue we dont how much of RLN was planned. The graphic on the website suggested we should have had a Consultation round 2 by the end of 2019 that would of have had the emerged Preferred Alignment and round 3 around mid-2019 with Construction Design and phasing. The TPAP was end of 2019 beginning of 2020. Its quite possible there is/was a Preferred Alignment document that showed that mythical 40m + deep tunnel that was never made public.
 
Is a tunnel boring machine capable of making such tight turns?
They can, but then the design of the TBM is highly compromised when doing much longer sections. To do the curves people are asking about means the TBMs themselves would have to be articulated in length of sections no longer than the cars planned for tunnel, and that presents immense problems. In practical terms, really tight turns would have to be bored manually, or by a machine or shield dropped down a vertical shaft at that point, which raises costs dramatically. This brings us back to @BurlOak 's continual point on modern cut and cover techniques, and how deep the tunnelling would be at certain points and if C&C would be more apt in those sections. It's apt you ask, because the TTC's alignment as published shows very sharp curves at points, ones that I intuitively guessed would be very difficult for TBMs to do. These problematic sharp turns are rampant in Ford's Fantasy Foible.

I see a number of very good TBMs engineering papers on-line, I'll read a few more before referencing.
Edit to Add: Catbus to the rescue yet again, and very germane to this discussion as the REM is his main muse:
[...]
People tend to think it’s the tunnels that are the most expensive part of underground systems like metros, but thanks to the already existing TBM technology, they often represent only a small portion of the overall cost. Sometimes as little as 10%
[....]
A large diameter tunnel becomes really interesting for the construction of a metro, if it is large enough to fit not only the tracks, but the station platforms inside it. This saves costs because it’s unnecessary to excavate large caverns, possibly dug from above requiring the purchase of a large amount of land. [...]
The cost of a TBM doesn’t get much higher as you increase its diameter. Tt is therefore cheaper to build one very large tunnel, rather than two smaller ones. So giant, linear tunnel building factories have been constructed, with some reaching up to 17.6m in diameter.
[...]
http://www.cat-bus.com/2018/01/far-from-boringmeet-the-most-interesting-tunnel-boring-machines/

As with the bridge controversy, one of the points remains the same: Once you have TBMs at work deep tunnelling, you keep them at that level unless you have a very real need to surface them, like a portal at the end of the underground section, not bringing them all the way up to cross a bridge to go all the way down again. For a deep river valley as you find on the northern leg, your bore depth in the surrounding area is not as deep as the valley floor you're going to traverse, so you *emerge* at near neutral grade to cross that valley, and in the case of the Leaside area crossing, the track would be run on embankment to allow level grade crossing for the various bridges needed to cross the DVP, Bayview, Bala Sub and Don River bridges before boring into the northern face of the valley to continue north.
The issue we dont how much of RLN was planned.
The issue is that for the "bridge" that was part of the TTC's planned Don Crossing is that the Don would be only crossed at one point.(By Eastern Ave) And the TTC had finalized and published their route for the DRL for all but a few small details. And it was the TTC's DRL (South) that Ford was referring to. The Relief Line North is and was always a Metronlinx project. Even DRL South was shared with the TTC when it became obvious that the TTC (and later City) were in over their bore depth.
 
Last edited:
Wonder if the foundations for the ICTS test track at Exhibition Place is still available? :D:D:eek:

From link.

The space age maglev system immediately won the interest of the Davis government, and in the Phase II proposals they selected it for further study, along with the Ford ACT and Hawker Siddeley's entry, both of which used rubber tires. Ford withdrew when the ICTS varied too greatly from the system it wanted to develop, which was aimed primarily at sites in the U.S. With only Hawker Siddeley and Krauss-Maffei remaining, the 1 May 1973 announcement that the Krauss-Maffei design had won the contest was unsurprising.

In November 1974 Krauss-Maffei announced that it was forced to withdraw from the project. The West German government had been funding development of several maglev systems based on different technologies, and decided at that time that Krauss-Maffei's system was less interesting than ones from Thyssen-Henschel and Messerschmitt-Bölkow-Blohm. There were also technical problems; in testing, the complex systems needed to switch trains on the magnetic tracks froze up, and would require a re-design. With Krauss-Maffei's financial support gone, and daunting technical problems remaining to be solved, the maglev project died. A test track being constructed on the grounds of the Canadian National Exhibition was abandoned in place, with the foundations and a few support pillars already constructed. Krauss-Maffei continued development of the original inter-city Transrapid, but at a very slow pace and through a series of mergers with other companies involved in maglev technology. The first Transrapid system did not enter service until 30 years later.

tspa_0112075f.jpg

Workmen prepare support bed for magnetic levitation train test track being built at the CNE
Innell, Reg
Picture, 1974, English

From link.
 
Last edited:
They can, but then the design of the TBM is highly compromised when doing much longer sections. To do the curves people are asking about means the TBMs themselves would have to be articulated in length of sections no longer than the cars planned for tunnel, and that presents immense problems. In practical terms, really tight turns would have to be bored manually, or by a machine or shield dropped down a vertical shaft at that point, which raises costs dramatically. This brings us back to @BurlOak 's continual point on modern cut and cover techniques, and how deep the tunnelling would be at certain points and if C&C would be more apt in those sections. It's apt you ask, because the TTC's alignment as published shows very sharp curves at points, ones that I intuitively guessed would be very difficult for TBMs to do. These problematic sharp turns are rampant in Ford's Fantasy Foible.

I see a number of very good TBMs engineering papers on-line, I'll read a few more before referencing.
Edit to Add: Catbus to the rescue yet again, and very germane to this discussion as the REM is his main muse:

http://www.cat-bus.com/2018/01/far-from-boringmeet-the-most-interesting-tunnel-boring-machines/

As with the bridge controversy, one of the points remains the same: Once you have TBMs at work deep tunnelling, you keep them at that level unless you have a very real need to surface them, like a portal at the end of the underground section, not bringing them all the way up to cross a bridge to go all the way down again. For a deep river valley as you find on the northern leg, your bore depth in the surrounding area is not as deep as the valley floor you're going to traverse, so you *emerge* at near neutral grade to cross that valley, and in the case of the Leaside area crossing, the track would be run on embankment to allow level grade crossing for the various bridges needed to cross the DVP, Bayview, Bala Sub and Don River bridges before boring into the northern face of the valley to continue north.
The issue is that for the "bridge" that was part of the TTC's planned Don Crossing is that the Don would be only crossed at one point.(By Eastern Ave) And the TTC had finalized and published their route for the DRL for all but a few small details. And it was the TTC's DRL (South) that Ford was referring to. The Relief Line North is and was always a Metronlinx project. Even DRL South was shared with the TTC when it became obvious that the TTC (and later City) were in over their bore depth.
If I understand this right, curves of radius above 300m can likely be bored. I was imagining a radius of about 100m (something that TTC subways can't handle, but these REM type trains can). Do they basically dig up the curve from above and built it cut and cover? The TBM then passes through this and continues on it's way on a tangent. It's work from above, but it's still faster than a station because it's just the tunnel that's poured and the rest just back-filled. The TBM also doesn't need to be dismantled to cross this space.

The other thing, as I understand it, is that taking the muck out of the shaft becomes harder as it becomes longer. TBM drive are usually kept below about 5km for this reason.

In terms of cut-and-cover, I worry it might not fly downtown. Would you TBM to City Hall, and then cut-and-cover the rest all the way to Ontario place. There must be a TBM extraction site somewhere, and then continue with cut-and-cover from there - and I am just not sure where that would be. Maybe Ford will just do the whole thing cut-and-cover (or allow the P3 contractor to use c-and-c), and figure he won't lose many votes if the locals complain.
 
It took some digging (pun unavoidable) and there's no shortage of excellent articles on TBM's, the trick is to find them relevant and applicable to the Ontario Line. The more I read, the more I realize the absurdity of what Ford is fondling. He needs a good slap from an engineer, not that he could ever understand why.

First the easy article to relate, this being the Melbourne metro project:
https://metrotunnel.vic.gov.au/construction/building-the-tunnels-and-stations/tunnel-boring-machines
https://metrotunnel.vic.gov.au/__data/assets/pdf_file/0007/357163/TBM-Fact-Sheet-A4-4pp-WEB-002.pdf

Very interesting reading, since it's obviously the product of informed engineers and planners, ones that can 'think in a straight line'...figuratively and factually. It has mild curves of course.

If I understand this right, curves of radius above 300m can likely be bored. I was imagining a radius of about 100m (something that TTC subways can't handle, but these REM type trains can).
Well here's where the mined muck hits the belt:
Urban EPB Tunneling in Limited Space:
A Case Study of the San Francisco Central Subway Project
Noah Johnson
The Robbins Company

ABSTRACT: The San Francisco Central Subway project is a challenging modern example of urban tunneling in limited space conditions. Two 6.3 m diameter Earth Pressure Balance Machines (EPBs) are excavating parallel 2.5 km long tunnels under low cover and in mixed ground conditions. The small launch site situated between an interstate and an off-ramp, highly curved tunnel alignment, and geology are particular challenges. These elements required customized tunnel and machine design, from TBM shipment and assembly, to launch and excavation. This paper discusses the project challenges and solutions at the Central Subway project, with a focus on TBM and continuous conveyor logistics. Requirements of the project include explosion-proof electrical components, laser-guided survey, rubber-tired supply vehicles, and machine and back-up solutions for steep inclines and tight curves.
[...]
[...]The tunnels will level out then take a sharp right turn (R 137 m) towards the north at Market Street, where they will pass under two other operational subway lines. In order to ensure the safety of those lines during boring operations, a liquid level system working in concert with longitudinal and transverse strain gauges and other instrumentation will be used to monitor ground disruption. The system will be used under the live tracks and determine if settlement mitigation measures must be executed
[...]
Due to the complex geometry of the alignment, steering the TBMs accurately through the tight curves (min R 137 m) is one of the key challenges of the project. To accomplish this it was necessary to articulate the TBM shields. An active articulation system was integrated as it allows the thrust cylinders to remain parallel to the tail skin and react evenly with the segments. This feature mitigates the risk of segment damage, ring deformation, or settlement during boring.
[...]
http://www.therobbinscompany.com/wp-content/uploads/2014/08/UrbanEPBs_NAT2014.pdf

For those unfamiliar, Robbins remain one of the most pre-eminent names in TBM manufacture.

You weren't far off with "100m" Burl, but 137 was the best they could do, and with *many* accommodations, expensive ones, to do it.

The long and short of this is that all those squiggles proposed for the O-Line on the map that come from peoples' imaginations are fantasy. Can it be done? Sure, at many multiples and complications of the price people are assuming. It's just not how you build a metro unless you go back to using a Greathead Shield:
https://en.wikipedia.org/wiki/Tunnelling_shield

Perhaps with Ford's ideas for education cut-backs and minimum wage, navvies can again be available to do this...

The other thing, as I understand it, is that taking the muck out of the shaft becomes harder as it becomes longer.
It's more a question of where to dump it than the extraction itself. For Crossrail, it was shipped by freight from within the tunnels to the mouth of the Thames some thirty miles away to create new islands in the estuary as wildlife sanctuaries. That's yet another advantage of boring to mainline standards.
In terms of cut-and-cover, I worry it might not fly downtown.
It sure wouldn't.

The Fantasy Factor increases geometrically every time the Ontario Line as presented is examined.

Addendum: The Sydney Metro, which will use the Alstom Metropolis rolling stock, virtually identical to Montreal's REM save for being many more cars in a train: (Note the "100 kph" speed)
Tunnelling

Sydney’s new metro railway will run through purpose designed and built tunnels.
A number of factors determine the tunnel route and alignment. These include:
  • the location, depth and structure of the stations
  • vertical track grade
  • rock conditions
  • track curvature, to allow train speeds of up to 100 kilometres an hour
  • the physical constraints of the route, including crossing under Sydney Harbour.
Stage 1: Sydney Metro Northwest
Tunnelling finished in January 2016 on Australia’s longest railway tunnels – twin 15 kilometre tunnels from Bella Vista to Epping as part of Stage 1 of Sydney Metro.
Stage 2: Sydney Metro City & Southwest
Tunnelling started in October, 2018 on the twin tunnels from Chatswood to Sydenham, including under Sydney Harbour and through the Sydney CBD.

Tunnel boring machine progress
[...Google maps and interactive panes...]

https://www.sydneymetro.info/tunnelling

TBM feature:
https://www.sydneymetro.info/files/tunnel-boring-machine-1-elizabeth
 
Last edited:
The most successful transit systems in the world are more real-estate development initiatives than transport initiatives (though they combine both.) In Japan and Hong Kong, the agency planning the transit owns the station lands and gets developers to build apartment/mall/office complexes on top of where the stations will go. The transit agency reaps both the ridership and the rents.

You really, really need to look at the kinds of densities (and size of development sites) in and surrounding MTR developments and compare that against what is envisioned in Toronto - and even MTR couldn't get away without government funding for their latest SCL project (which BTW, is overdue and overbudget by 25%). Not to say we couldn't learn from them - just be extra diligent when you use examples from fundamentally different contexts.

AoD
 
Last edited:
  • Like
Reactions: syn
...
The most successful transit systems in the world are more real-estate development initiatives than transport initiatives (though they combine both.) In Japan and Hong Kong, the agency planning the transit owns the station lands and gets developers to build apartment/mall/office complexes on top of where the stations will go. The transit agency reaps both the ridership and the rents.
...

In North America, the governments went after the electric companies who also had streetcars, radials, interurbans, amusement parks, and residential and office developments as being "trusts", and needed to be dismantled. Not so in the rest of the world.
 
I dont understand the obsession with this line intersecting with the existing GO?Smarttrack stations? Exhibition/Liberty GO.

I think it really doesnt offer much benefit in terms of inter-modality. I dont think many people wish to transfer to these stations, when they could just take the trains from these to Union already. They basically go to the same place.

Id rather see a stop in the heart of Liberty, at the parking lot of Atlantic/East Liberty, and a stop right at Ontario Place.
 
I dont understand the obsession with this line intersecting with the existing GO?Smarttrack stations? Exhibition/Liberty GO.

I think it really doesnt offer much benefit in terms of inter-modality. I dont think many people wish to transfer to these stations, when they could just take the trains from these to Union already. They basically go to the same place.

Id rather see a stop in the heart of Liberty, at the parking lot of Atlantic/East Liberty, and a stop right at Ontario Place.
It's redundancy. Also, some on LSE, who are going to City Hall, may want to make the transfer here - it would relieve Union a bit. A similar argument could be made that having an Ontario Line station on the other rail corridor may have some benefit.
 
I thought they are planning a GO station at Front and Spadina. How realistic would it be to have a station there to connect with this GO station instead of the one listed at King and Bathurst?
 
I dont understand the obsession with this line intersecting with the existing GO?Smarttrack stations? Exhibition/Liberty GO.

I think it really doesnt offer much benefit in terms of inter-modality. I dont think many people wish to transfer to these stations, when they could just take the trains from these to Union already. They basically go to the same place.

Id rather see a stop in the heart of Liberty, at the parking lot of Atlantic/East Liberty, and a stop right at Ontario Place.

Union is not going to get less passengers, so having as many RT lines connecting to GO RER makes sense.
 

Back
Top