UtakataNoAnnex
Senior Member
And goodness, next time we all should meet up and have a picnic there...The last two could go into the West Don In TE Seaton park thread. They've been backfilling the diversion path the past few weeks
And goodness, next time we all should meet up and have a picnic there...The last two could go into the West Don In TE Seaton park thread. They've been backfilling the diversion path the past few weeks
This seems like a good idea to dispel my sense that if ML were to resell unchanged, expropriated properties for a profit, that ithat would constitute a form of corruption.As far as the expropriations go, is there anything stopping the current owners negotiating that Metrolinx offer them right of first refusal on the property at the expropriated price? That provides an option for the seller to regain what they had should the works not cause any fundamental damage.
Of course, the neighbouring properties will have appreciated but the current owners will have had to find somewhere else to live in the meantime, so the gain they might seen to be making should be tempered by those outgoings. Metrolinx does lose out on the opportunity to make a capital gain but if they make a high enough offer to the seller, maybe they won’t have to worry about the option being exercised as the prior owner might actually be able to find something else in this god awful market.
At the end of this video the reporter says Verster wouldn't commit to the 2031 opening date for the OL and that there is a lot of work to do still
At the end of this video the reporter says Verster wouldn't commit to the 2031 opening date for the OL and that there is a lot of work to do still
I mean it doesn’t mean it won’t open in 2031, just that Metrolinx can’t commit to that date because, well, it’s 7 years away and the construction of the line is really just getting started.
Setting a hard deadline 8-10 years out is ridiculous on an $11+ billion project.This is non-sense. It doesn't matter how big a project is, they should have a plan on when things will be completed and be held to that. One can only hope he's not committing to a date because of the complete embarrassment that is the crosstown and not because they've already encountered set backs on the OL.
Setting a hard deadline 8-10 years out is ridiculous on an $11+ billion project.
The line will likely open around then and I'm sure 2031 is the target date, but a million things can happen on projects. Metrolinx and the TTC have been burned bad by the media on promising opening dates enough times now that they don't want to discuss them any longer. Target opening dates have always been that, targets - but the media treats it as a profound failure to miss it.
This far out they can never be more than an approximate target, and it's very possible it happens. Finch is opening basically on time, for example, but large infrastructure projects often hit snags and delays which are basically unavoidable and uncontrollable. It happens when timescales are that large.
The Crosstown is a fairly extreme version of a delayed project which is why I think so many people are so sensitive to it in the City right now. Most of the time a project isn't 3-4 years late like the Crosstown, more like 6 months or a year. And the latter is very common. There is no reason to believe the OL will be a repeat of the Crosstown, in fact, it should be the opposite as Metrolinx has applied a lot of lessons learned from the Crosstown to the OL in it's design to avoid the critical delays that the Crosstown faced.
Choosing Acciona to build part of the Ontario Line would say otherwise, and that Metrolinx sure as hell as not learned anything.Setting a hard deadline 8-10 years out is ridiculous on an $11+ billion project.
The line will likely open around then and I'm sure 2031 is the target date, but a million things can happen on projects. Metrolinx and the TTC have been burned bad by the media on promising opening dates enough times now that they don't want to discuss them any longer. Target opening dates have always been that, targets - but the media treats it as a profound failure to miss it.
This far out they can never be more than an approximate target, and it's very possible it happens. Finch is opening basically on time, for example, but large infrastructure projects often hit snags and delays which are basically unavoidable and uncontrollable. It happens when timescales are that large.
The Crosstown is a fairly extreme version of a delayed project which is why I think so many people are so sensitive to it in the City right now. Most of the time a project isn't 3-4 years late like the Crosstown, more like 6 months or a year. And the latter is very common. There is no reason to believe the OL will be a repeat of the Crosstown, in fact, it should be the opposite as Metrolinx has applied a lot of lessons learned from the Crosstown to the OL in it's design to avoid the critical delays that the Crosstown faced.