I'll see if I can grab some pics tonight after work, but in the last two weeks there has been a lot of progress I've noticed:
- Concrete poured around the footings for the steel supports on the east and west sides of the heritage structure
- The center steel supports have had caps welded on them similar to the east and west side. They've also dug a trench slightly north which has other footings - it has also been filled with concrete
- I believe shoring has wrapped up on the south side of the site, if not, it's ~90% done
- Excavation has begun on the west side of the site
I'd expect the final steel supports to arrive soon and final demolition to follow shortly thereafter!